Roads on a housing estate in Alsager often used by drivers as a cut-through are due to be adopted by Cheshire East Council next summer – five years after the development was built.
A spokesperson for housebuilder Wain Homes reconfirmed that there were no plans to restrict access to residents only, or put up additional signage on Richard Woodcock Way, which had been previously requested by Alsager Town Council.
As we reported earlier this year, members of the council felt that Wain Homes had “missed the point” of its email sent to the developer to ask when the road would be adopted onto Cheshire East’s highway network.
Road adoption is a legal process where a local council takes over the ownership and future maintenance of a private road, making it part of the public highway.
Couns had asked whether “residents only” signs could be installed following complaints that drivers travelled too fast along the road and used it as a cut-through to Sainsbury’s, off Linley Lane.
The developer responded to explain that it had no plans to put up additional signage, as use of the road was not restricted to residents.
It also blamed delays to the road being adopted on non-flushable materials being put into the sewer system, which had prompted an investigation into a blockage by United Utilities.
In an update from Wain Homes to the town council, which was discussed at its most recent Planning, Environment and Communities committee meeting, a spokesperson for the developer said: “We can confirm that we currently anticipate adoption of both the estate roads and sewers across the entire development, including Richard Woodcock Way, during summer 2027.
“This remains subject to the completion of the statutory maintenance periods (12 months) and the final adoption processes undertaken by the relevant authorities.”
It reiterated its previous statement that Richard Woodcock Way was a public highway with no access restrictions in place.
It said: “The development has been constructed in accordance with the approved highway design and legal agreements; all required highway works and signage have been installed in accordance with the legal agreement and plans.
“As such, there are no proposals to install any additional highway signage or restrict access to residents only.”
It said its previous statement regarding the drainage issues on site had been intended to “share guidance” with residents on “sewer misuse”.
“As previously advised, investigations into the reported blockages identified the presence of non-flushable materials within the sewer network,” the spokesperson said.
“Raising awareness of the correct use of the drainage system can help minimise the likelihood of similar issues occurring in the future.”
When asked why the road had not been adopted in the last five years, a spokesperson for Cheshire East Council said in a previous statement: “Before roads in new developments are adopted as public highway, we carry out inspections to ensure they meet the required standards.
“As part of routine inspections of Richard Woodcock Way in Alsager, we identified drainage works that need to be completed before the road can meet that standard.
“While we cannot require these works to be completed within a specific timescale, we will continue to work with the developer to support progress.